Ten-day iron-ore rail corridor maintenance to start on October 16

Views : 369
Update time : 2020-10-14 18:17:44

Transnet Freight Rail (TFR) has advised that it will conduct a ten-day shutdown on the iron-ore rail corridor from October 16.

During this time, the State-owned utility’s scope of maintenance work will include replacing 30 623 sleepers, three turnouts, 5 km of catenary wire, 1.2 km of contact wire and 870 insulators, as well as doing ballast screening, tamping and regulation on many kilometres of track.

Part of this year’s maintenance will include the installation of a permanent bridge to replace a temporary emergency bridge that was installed at Vredendal.

The emergency bridge was installed after an incident occurred in November last year, whereby an abnormal low-bed vehicle loaded with an excavator collided with and damaged the bridge deck.

TFR conducts annual scheduled maintenance on the corridor, which stretches 861 km from Sishen, in the Northern Cape, to Saldanha, in the Western Cape. 

Related News
Read More >>
South Africa’s coal exports rise on improved rail performance South Africa’s coal exports rise on improved rail performance
Jan .30.2026
South Africa’s coal exports rise on improved rail performance
Ukrainian industry to drive postwar recovery Ukrainian industry to drive postwar recovery
Jan .30.2026
Ukrainian industry to drive postwar recovery
Hindalco invests Rs 21,000 crore to expand aluminum production in Odisha Hindalco invests Rs 21,000 crore to expand aluminum production in Odisha
Jan .30.2026
Hindalco invests Rs 21,000 crore to expand aluminum production in Odisha
Taiwan’s Yusco largely raises stainless steel prices for Feb as raw material costs soar Taiwan’s Yusco largely raises stainless steel prices for Feb as raw material costs soar
Jan .30.2026
Taiwan’s Yusco largely raises stainless steel prices for Feb as raw material costs soar